A renovation schedule is not one length of time. It is a chain of stages, each waiting on something specific, and most of the months go to the waiting rather than to the work.
The two ranges, and what they cover
CAS publishes two durations and plans against them. They are worth reading carefully, because what they include is as important as how long they are.
The two ranges CAS plans against
- 2 to 4 months
- Design, planning and permits
- 4 to 8 months
- Construction, full home
The first covers design, planning and permits as one span. They are quoted together because they overlap: the drawings develop, the engineering lands, and the application goes in while selections are still being settled.
The second covers construction on a full home, from the first day on site to the final inspection. It begins when the first one has produced something a trade can build from.
Both are whole-house figures, and that is the part most often misread. A single room is not a fraction of them. A bathroom skips almost none of the stages, so its schedule is dominated by the same waiting with less work inside it.
Which is why a number quoted in conversation is usually wrong in a predictable direction. It describes the construction and leaves out everything in front of it.
The stages, in the order they happen
Every renovation runs through the same sequence, whatever its size. The lengths change; the order does not.
Brief and feasibility. What you want, what the house and the zoning allow, and whether the two can be made to agree.
Design. Layout resolved to the point where someone could price it, which is a long way past the point where it looks finished.
Engineering and documentation. Structure drawn and sealed, services laid out, and the energy compliance path stated.
Permit application and review. The set goes in, the City reviews it, and clarifications come back.
Procurement. Long-lead items ordered against a date, trades booked, and allowances turned into actual products.
Site setup and demolition. Protection, services isolated, hazardous material cleared, and the house opened up.
Structure and rough-ins. Framing, then electrical, plumbing and mechanical, each inspected before anything covers it.
Close and finish. Insulation, drywall, millwork, tiling, painting and the fittings, in that order and not in parallel.
Final inspection and close-out. The permit is closed, the list from the walkthrough is worked off, and the house comes back.

What each stage is waiting on
A stage does not take its time because the work is slow. It takes its time because it is waiting on a specific thing, and naming that thing is how you find out whether your schedule is honest.
The real dependency at each point
- Design waits on decisions
- Not on drawing. A layout cannot be resolved while two options are still open, and the pause between the question and your answer is the whole delay.
- The permit waits on completeness
- A set that answers every question moves through once. A set missing a seal or a detail comes back out, gets corrected, and rejoins the queue behind whatever arrived meanwhile.
- Procurement waits on selections
- The order date is downstream of the decision date. Cabinetry, stone, windows and specialist fittings are made after they are ordered, so a late choice moves the installation, not the order.
- Rough-ins wait on inspection
- Nothing gets covered before it has been looked at, and inspections are booked rather than summoned. The trade whose work is being inspected cannot start the next thing yet.
- Finishing waits on everything arriving
- The final stage looks slow because it is where every earlier delay has collected. One missing item can hold a room that is otherwise complete.
- Close-out waits on the list
- A walkthrough produces a list, and the list has items on it that need a tradesperson back on site. That return visit is scheduled around their other work.
Which delays are yours
This is the division worth having clear before you start, because the two halves need completely different responses. One you manage. The other you build room for.
Where the time actually goes
Nothing in the right-hand column is a reason for a schedule to be vague. It is a reason for a schedule to name them and leave room, rather than assume every one of them goes perfectly.
Yours to control
- How quickly you answer a question that has a trade waiting behind it
- Whether selections are locked before the order window closes
- Whether the scope changes once the walls are open
- How complete the application is when it goes in, which follows from how settled the design was
- Whether a contingency exists for what demolition finds, or whether finding it starts a new conversation
- How early a strata is approached, where the building has one
Not yours to control
- How long the City's review queue takes at the moment you join it
- Clarifications a reviewer asks for, and the round trip they add
- When an inspector is available, on each separate permit
- Manufacturing and shipping on anything made to order
- Weather, where the work is exterior or the structure is exposed
- What is behind the walls, which is discovered rather than scheduled

Where months are actually found
Nobody finds time by working faster on site. The trades are not the bottleneck, and asking them to be is how quality goes.
Time is found in overlap, and there are only a few places it is available. The application can be prepared while the design is still moving. Long-lead items can be ordered before demolition rather than after it. Separate permits can run alongside each other.
Design, engineering and permitting are CAS's own work rather than something handed to a third party, which is what makes that overlap practical. The same people hold the drawings, the engineering and the application, so the application is not waiting on a handover.
The other place time is found is less comfortable: deciding earlier. A choice made on paper costs a conversation. The same choice made on site costs the work already done, and the queue behind it.
Where this sits in a project

Where your own months will go
If you want a realistic schedule for your own house, build it the way a builder does. Start from the stages above, and for each one write down what it is waiting on.
Then look at where your project is unusual. Structural work, a change of use, a heritage review or a strata each add a dependency rather than a percentage. A dependency is something that either lands or does not.
A schedule built that way is longer than the one you hoped for and shorter than the one you will get if nobody writes it down. It also tells you, on any given week, what the project is actually waiting for.
That last part is worth more than the total. A renovation feels long mainly when you cannot see what it is waiting on.
Ask what the project is waiting on this week. If the answer is a decision, it is yours. If it is an approval, it is a date someone else holds.

